You don't have javascript enabled. Good luck with that.
Pencarian
 Pembangunan Stadion Kita Capai 68,95 Persen
....
photo Aldi Geri Lumban Tobing - Beritajakarta.id

JIS Construction Progress Hits 68.95 Percent

Construction of Jakarta International Stadium (JIS) or called Stadium Kita is entering 104th week where it touches 68.95 percent. The construction is currently entering the main work stage for structural works such as casting and flooring. There is also stadium stand precast installation which is expected to accommodate up to 82,000 people.

We are optimistic, because during the pandemic, collaboration is the key

JIS Project Director, Iwan Takwin mentioned, the main field is now being constructed, from dredging, drainage installation, coral layer installation, and others.

"We continue to work in the midst of various challenges during the pandemic. In the 103rd week, accumulative progress has reached 68.05 percent, Tuesday (8/31).

Thousands JIS Construction Workers Vaccinated Against COVID-19

According to him, PT. Jakarta Project (Jakpro) is optimistic that JIS/Stadium Kita construction will be completed on target. Although there were many challenges during the construction, ranging from unpredictable weather to prolonged COVID-19 pandemic.

"COVID-19 pandemic also has implications for material delays or project logistics from the country of origin," he added.

Number of workers were also declined because some of them chose to quit to return to their hometowns.

"From total 2,000 workers decreased to 1,500 workers during the pandemic. It becomes our challenge since the construction work must be completed on target," he asserted.

Even so, PT. Jakpro together with Joint Operation (KSO) for JIS Project carried out various innovations and strategies thus construction of this FIFA-standard stadium remained productive and could be completed on target.

"We are optimistic, because during the pandemic, collaboration is the key. This way, we can mitigate any challenges and potential delays from the start," he conveyed.

His side also tightened health protocols in Stadium Kita project area. Project area is made sterile because only field workers are allowed to enters. In addition, its facilities are also sprayed with disinfectant twice a week.

The management, he continued, also carries out health monitoring twice a day, from checking worker's body temperature, health, and requiring workers to report their condition to contractor's PIC.

"Workers who have just arrived at project site will undergo self-isolation for two weeks. During observation period, workers are still working in separate area that don't mix with other workers. While suppliers and guests who come to the project site are required to bring result of antigen test or antibody rapid test that has been taken a day before," he explained.

Linked News
Popular News indeks
  1. Mothers Attack Cheap Market in Cibubur Urban Village

    access_time02-05-2024 remove_red_eye798 personNurito
  2. Sunny All Day Long in Jakarta

    access_time03-05-2024 remove_red_eye544 personAnita Karyati
  3. Distamhut Plants 150 Trees in Five City Areas Simultaneously

    access_time03-05-2024 remove_red_eye453 personAldi Geri Lumban Tobing
  4. Green Belt Arrangement on Jalan Panjang Duri Kepa Reaches 40 Percent

    access_time03-05-2024 remove_red_eye407 personTP Moan Simanjuntak
  5. W. Jakarta Bina Marga Sub-agency Repairs Kembangan Outer Ring Road Section

    access_time07-05-2024 remove_red_eye296 personTP Moan Simanjuntak